effective device capacity – seemingly plenty for the next 12 months.
device pools silently growing faster than usual.
of emergency storage that would have been needed if pool growth remained hidden.
Most capacity planning is done at the device level. But sometimes there are warning signs hiding under the surface.
For this company, Visual One Intelligence®’s® capacity planning tools and consulting helped them look deeper and avoid a major problem – one that would have cost $1 million to address.
SCALE OF THE PROBLEM
65% of IT leaders do not feel confident in their capacity planning forecasts.
OUTAGE RISKS
30% of application downtime can result from under-provisioning and insufficient capacity planning.
POTENTIAL GAINS
IT costs can be reduced by 25% when effective capacity planning is applied.
Like most teams, this enterprise infrastructure staff typically limited their capacity planning to the device level. During a recent capacity planning review, they looked at one of their 60+ devices and found no significant growth.
At only 66% effective capacity used with minimal 12-month growth, this NetApp device was not projected to increase more than a couple of percentage points within the next 12 months. In other words, everything looked fine!
Because they use Visual One Intelligence® to do capacity planning, however, they received an alert for the device indicating that some of it’s pools are expected to need additional capacity in the next six months. Although the device analysis showed no signs of upcoming growth, they decided to dive into Visual One Intelligence®’s® Capacity Planning by Pool reports.
Out of more than 25 pools, most were barely used and some even trended negative. Everything must be fine, right?
Wrong.
Four outlier pools reported significant growth trends – so significant that another six months of similar growth would require another 900 TB of effective storage for the device to function. And to get that much effective storage, they would need to purchase over a petabyte of total space to cover the overhead.
Without Visual One Intelligence®, they would not have noticed this until the last minute. They likely would have faced a $1,000,000 unplanned purchase.
Instead, Visual One Intelligence®’s® premiere capacity planning features – plus detailed best-practice alerting – warned them half a year in advance so they had time to prepare and make adjustments.